supply and installation of pumps, water lines, and collection tanks for water conveyance from wells field at Salsalah & Thamad

  • Contract Amount

    25,338,381 SAR

  • Project Duration

    12 Months

  • Client

    NWC

  • Consultant

    Engineering & Tech Services Offices Consulting Engineers

  • Contract start Date

    13-02-2019

  • Completion Date

    11-06-2020

  • Location

    Salsalah & Thamad

  • Overall Project Purpose

    • Conveying water line comprising supply and laying of 10 kilometer different sizes iron pipes in trenches that shall be excavated as part of the contract.
    • Electrical & Mechanical works for 9 wells.
    • Supply & installation of pumping station comprising 3 horizontal case pumps.
    • Erection of the pumping station building.
    • Supply & installation two 2000m3 GLS tank.
    • SCADA control system.