water supply enhancement program (RWSE) project in Riyadh
-
The project is a subcontract to JV Nesma & Wetico for designing and building the power package at 12 Different sites in Riyadh.
-
Project value
60,250,000 SAR
-
Client
NWC
-
Project Duration
6 Months
-
Start Date
1 Mar 2013
-
Finish Date
30 Sep 2013
-
Each of the 12 sites comprises the electromechanically reacted works of supplying and installing the following:
- 28 Containerized Generators Complete With All Accessories And Storage Tanks.
- MV (13.8KV) Switchgear.
- Step-down & Step-up Transformers.
- Main Distribution Boards, MCC, ATS.
- Hoists, Ultrasonic Level Meter And Flow Meter And All Associated Power And Control Cabling Works.